Industrial Boiler Repair - Cyclone Replacement
During 2022 Shelley Consulting were contracted to deliver project managment support to replace athe cyclones for a 122MW CFB-boiler at a combined heat and power station in Northern Stockholm. The project was fast-tracked in order to ensure that the owners of the power plant could return the plant to normal production at the start of the autumn season for district heating.
Our project manager from Shelley Consulting set the technical requirements, supported the procurement of the contractors and managed them throughout the manufacturing and construction stages. The boilers’ integrity was successfully restored during one month of intense construction activity comprising lifting out the old material, lifting in the new large steel segments which were then welded to form a circular cyclone steel structure inside the boiler. The project was completed in 3 months from start to finish.